Project name: | Depot object Ruzyně Prague |
---|---|
Year: | 2023 |
Location: | Praha |
GFA: | 9 036 m² |
GBA: | 43 085 m³ |
Zone: | 3 |
LoD: | 3,2 |
Output: | Model, 360° tour |
Input: | DWG, Point Cloud |
The model was created for the architectual study and subsequent phases. It includes the building model, model of paved surfaces and landscape model. Section affected by the future project was measured by a stationary laser scanner in S-JTSK coorditanate system. The rest of the building was modelled in lower detail based on the 2D documentation. All of the elements were classified into a classification system chosen by the client. The set of the models was handed out in IFC format.
Project name: | Pavilion ON, Mladá Boleslav |
---|---|
Year: | 2023 |
Location: | Mladá Boleslav |
GFA: | 15 039 m² |
GBA: | 22 706 m³ |
Zone: | 2 |
LoD: | 3, 2, 1 |
Output: | Model, 360° tour |
Input: | DWG, PDF, Point Cloud |
The model was created for the architectual study and subsequent phases. It includes 3 separated models of structual solution of buildings affected by the project and site model divided into three models - paved areas model, landscape model and model of surounding buildings. The buildings were measued by a stationary laser scanner in S-JTSK coordinate system by which all the models were interconnected. Scan by a total station and a drone were made for the surrounding areas and small exterior elements. All of the model elements were classified into a classification system chosen by the client. As-built 2D documentation was generated from the models.
Project name: | Lučenec OÚ |
---|---|
Year: | 2023 |
Location: | Lučenec |
GFA: | 9 255 m² |
GBA: | 37 707 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | Point Cloud |
The model was created for the architectual study and subsequent phases. It includes the building model and site model of outdoor area. The buildings were measured by a stationary laser scanner in S-JTSK coordinate system. For the surrounding areas and small exterior elements a topographical survey was taken. Due to non-uniform room accessibility, the quality and correctness of the point cloud was check via the polygon made by a total station.
Project name: | Administration Kbely, Prague |
---|---|
Year: | 2023 |
Location: | Praha |
GFA: | 4 928 m² |
GBA: | 15 424 m³ |
Zone: | 3 |
LoD: | 4, 3 |
Output: | Model, 360° tour |
Input: | Point Cloud |
The model was created for the architectual study and subsequent phases. It includes six independent models (construction, HVAC) and site model containing model of paved areas and landscape model. The adminitrative building was measured by the stationary laser scanner in S-JTSK coordinate system by which all the models were inteconnected. For the surrounding areas and small exterior elements a topographical survey was taken. The set of the models was handed out in IFC format.
Project name: | Lovosice - hostel |
---|---|
Year: | 2022 |
Location: | Lovosice |
GFA: | 4 874 m² |
GBA: | 16 004 m³ |
Zone: | 3 |
LoD: | 4 |
Output: | Model |
Input: | DWG, PDF |
The model was created as a carrier of information for facility management. The basis was the drawing documentation of the actual construction and data from the construction process. Non-graphical information was specified and communicated in detail with the client. The model contains the technical equipment of the building. All elements are sorted according to the SNIM system.
Project name: | Theater BP, Brno |
---|---|
Year: | 2022 |
Location: | Brno |
GFA: | 3 598 m² |
GBA: | 22 583 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | DWG, PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The building is located in an urban courtyard. A stationary laser scanner was used for its measurement, and the connection of the individual floors was made possible thanks to the accesses to the neighbouring buildings.
Project name: | Administrative building, Zlín |
---|---|
Year: | 2022 |
Location: | Zlín |
GFA: | 11 310 m² |
GBA: | 41 682 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | DWG, PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The building was measured with a stationary laser scanner. Where the operation could not be restricted two scanners were used and a timetable and a flow chart was created.
Project name: | Department store Třebíč |
---|---|
Year: | 2022 |
Location: | Třebíč |
GFA: | 6034 m² |
GBA: | 27 038 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | PDF, Point Cloud |
The model was created as a basis for the architectural study and management of the building. A stationary laser scanner was used for its measurement. In parts of the building that were inaccessible, archival documentation was used. All work was carried out during it's operation.
Project name: | Charity Bratislavská Brno |
---|---|
Year: | 2022 |
Location: | Brno |
GFA: | 2732 m² |
GBA: | 12 235 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, DWG, PDF, 360° tour |
Input: |
The model was created as a basis for the architectural study and subsequent phases. The model includes a building with a decorative facade and adjacent service areas. The building, along with the exterior areas, was surveyed with a stationary laser scanner. All work was carried out during it´s operation. Drawings were generated from the model for facility management.
Project name: | MNNP, Praha |
---|---|
Year: | 2022 |
Location: | Praha |
GFA: | 5993 m² |
GBA: | 20 244 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | DWG, PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The client defined the floors and technologies that needed to be recorded in greater detail. The rest of the building was based on archival drawings. A stationary laser scanner was used to survey the building, adjacent exterior areas and building facades. The more distant portions of the site were modeled based on a topographic and elevation survey. All work was carried out considering the hospital operation and inpatients.
Project name: | Interiors Wolf Brno |
---|---|
Year: | 2022 |
Location: | Brno |
GFA: | 990 m² |
GBA: | 3 543 m³ |
Zone: | 2 |
LoD: | 2 |
Output: | Model, DWG, PDF, 360° tour |
Input: |
The model was created as a basis for an architectural study. The building was modelled on the basis of archival drawings with verification of dimensions by on-site measurements and photo documentation. All work was carried out during it's operation.
Project name: | Troubsko library |
---|---|
Year: | 2022 |
Location: | Troubsko |
GFA: | 500 m² |
GBA: | 1 117 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, DWG, PDF, 360° tour |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model included the building and adjacent service areas. The building, along with the outdoor areas, was surveyed with a stationary laser scanner.
Project name: | Hotel International - wellness, Brno |
---|---|
Year: | 2022 |
Location: | Brno |
GFA: | 1 763 m² |
GBA: | 6 383 m³ |
Zone: | 1 |
LoD: | 3 |
Output: | Model |
Input: | Point Cloud |
The model was created as a basis for an architectural study. The assignment did not concern the whole building, but only a section of two floors, which was scanned with a stationary scanner. The client defined the model categories and their detail.
Project name: | Kolej K2, České Budějovice |
---|---|
Year: | 2022 |
Location: | České Budějovice |
GFA: | 6 277 m² |
GBA: | 18 289 m³ |
Zone: | 4 |
LoD: | 3 |
Output: | Model, DWG, PDF, 360° tour |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The building was scanned with a mobile scanner and connected to S-JTSK. Drawings were provided to the client together with the model.
Project name: | MO, Kbely airport |
---|---|
Year: | 2022 |
Location: | Praha |
GFA: | 18 927 m² |
GBA: | 101 977 m³ |
Zone: | 2 |
LoD: | 2 |
Output: | Model, DWG, PDF, 360° tour |
Input: | Point Cloud |
Passport dealt with 12 objects within the area of the military airport Kbely. During the passport, non-graphical information of individual buildings and the positions of technical equipment were noted. The buildings were scanned by mobile scanner and linked to S-JTSK. All the work was carried out while in operation. Together with the models, drawings and technical description of the buildings were provided to the client.
Project name: | APC Václav Havel Airport Prague |
---|---|
Year: | 2022 |
Location: | Praha |
GFA: | 14 560 m² |
GBA: | 68 468 m³ |
Zone: | 4 |
LoD: | 2 |
Output: | Model |
Input: | DWG, PDF, Point Cloud |
The model was created for facility management, then for the layout modification and reconstruction of the building. All documents were supplied by the client as well as the extensive BIM model specification for both the graphical and non-graphical parts. Each element has its own classification according to the client's system.
Project name: | Nové město nad Metují |
---|---|
Year: | 2022 |
Location: | Nové město nad Metují |
GFA: | 2 023 m² |
GBA: | 6 986 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, DWG, PDF |
Input: | PDF, Point Cloud |
The model was created as a basis for construction documentation and subsequent reconstruction of all objects on the property. Three separate building models were created, which were not interconnected. The input data were from a mobile scanner that the client had available.
Project name: | Anatomy LF OU, Ostrava |
---|---|
Year: | 2022 |
Location: | Ostrava |
GFA: | 1 188 m² |
GBA: | 4 574 m³ |
Zone: | 2 |
LoD: | 2 |
Output: | Model |
Input: | DWG, PDF |
The model was created as a basis for an architectural study. The specified detail did not require the verification of the building dimensions by means of laser surveying and on-site photo documentation. The model was based on archived drawings.
Project name: | Building G FCH BUT, Brno |
---|---|
Year: | 2022 |
Location: | Brno |
GFA: | 1 183 m² |
GBA: | 6 802 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. It includes two separate building models and a site model of outdoor areas. All models are interconnected by S-JTSK. The building were scanned by a stacionary laser scanner and linked to the S-JTSK. For the adjacent areas and small exterior features, a topographical survey was taken.
Project name: | Administration Náchod |
---|---|
Year: | 2022 |
Location: | Náchod |
GFA: | 8 528 m² |
GBA: | 31 622 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, DWG, PDF, 360° tour |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. It contains a large building with a diverse layout and a situation model of outdoor areas. The models are interconnected. Objects with outdoor areas were scanned with a stationary laser scanner. All work was carried out during buillding normal operation. An ifc model and drawing documentation were generated from the model.
Project name: | Dance Conservatory, Prague |
---|---|
Year: | 2022 |
Location: | Praha |
GFA: | 15 093 m² |
GBA: | 72 456 m³ |
Zone: | 4 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The level of detail of the building was defined by floors, where level of detail 3 and above was required, a stationary laser scanner was used. Archival drawings were used for Level 2 floors. All work was carried out on the fly.
Project name: | Lužná and Plotní apartment buildings |
---|---|
Year: | 2021 |
Location: | Brno |
GFA: | 1593 m² |
GBA: | 6145 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, DWG, PDF |
Input: | Point Cloud |
Models were created for facility management. Both buildings were made based on the mobile scanner data available to the client. Simplified drawings were generated from the models.
Project name: | SŽ Horní Heršpice |
---|---|
Year: | 2021 |
Location: | Horní Heršpice |
GFA: | 1601 m² |
GBA: | 5507 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model included the building and adjacent service areas. The building, along with the outdoor areas, was surveyed with a stationary laser scanner.
Project name: | Magnetic resonance pavilion Hodonín |
---|---|
Year: | 2021 |
Location: | Hodonín |
GFA: | 15 840 m² |
GBA: | 73130 m³ |
Zone: | 2 |
LoD: | 2 |
Output: | Model |
Input: | DWG, PDF |
The model was created as a basis for the architectural study and subsequent phases. The modelled building was to be connected to the newly designed building. Great emphasis was put on the measurement of outdoor spaces and both vertical and horizontal communications. A topographic plan was created for the outdoor areas. The interior communications were surveyed with a stationary scanner. The wider context within the site was created in a separate model of lower detail. All work was carried out whilst the site was operational.
Project name: | Prague Funeral Parlor |
---|---|
Year: | 2021 |
Location: | Praha |
GFA: | 3385 m² |
GBA: | 13 319 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | model, dwg, pdf |
Input: | pdf + mračno |
Project name: | Albatros, Jeseník |
---|---|
Year: | 2021 |
Location: | Jeseník |
GFA: | 5312 m² |
GBA: | 19 926 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model included a building with a decorative facade and adjacent service areas. The building, along with the exterior areas, was surveyed with a stationary laser scanner. To add information regarding the relationship to the surrounding terrain and outdoor utilities a topography plan was created.
Project name: | Apartment building Pěkná |
---|---|
Year: | 2021 |
Location: | Pěkná |
GFA: | 647 m² |
GBA: | 2031 m³ |
Zone: | 2 |
LoD: | 2 |
Output: | Model, DWG, PDF |
Input: | Point Cloud |
The model was created for building management and rental unit inventory. The building was made based on the mobile scanner data available to the client. Simplified drawings were generated from the models.
Project name: | Sedlčánky |
---|---|
Year: | 2021 |
Location: | Sedlčánky |
GFA: | 978 m² |
GBA: | 4123 m³ |
Zone: | 4 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | DWG, PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model included a building with a decorative facade and adjacent service areas. The building along with the exterior areas was surveyed with a stationary laser scanner and the topography plan of the property was used for the more distant areas. Drawings were generated from the model.
Project name: | NEM Znojmo |
---|---|
Year: | 2021 |
Location: | Znojmo |
GFA: | 3512 m² |
GBA: | 14 843 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | DWG, PDF, Point Cloud |
The model was created for building management. The client provided the original project documentation, which was verified by a stationary laser scanner. Elements of interest to the client were tagged for management and the procedure for implementing the ifc model into the specified software was described.
Project name: | NDFM, Nová scéna |
---|---|
Year: | 2021 |
Location: | Frýdek - Místek |
GFA: | 5191 m² |
GBA: | 30 869 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, DWG, PDF |
Input: |
The model was created on the basis of an architectural study. It was a conversion of 2D drawings into 3D form. Individual drawings and 3D schematics were then prepared in the model for the necessary presentation of the project to the client.
Project name: | Ruzyně, prst C |
---|---|
Year: | 2021 |
Location: | Praha |
GFA: | 15 024 m² |
GBA: | 102 137 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model |
Input: | pdf + Point Cloud + VP |
The model was created for facility management. All documents were supplied by the client, as well as an extensive BIM model specification for both the graphical and non-graphical parts. Each element is classified according to the client's system.
Project name: | Teplice |
---|---|
Year: | 2021 |
Location: | Teplice |
GFA: | 881 m² |
GBA: | 2 478 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | DWG, PDF |
The model was created as a basis for the architectural study and subsequent phases. The model included the building and adjacent service areas. The building along with the outdoor areas was modelled based on the archival documentation. The dimensions of the individual rooms were verified by on-site measurements.
Project name: | Government Press Room |
---|---|
Year: | 2021 |
Location: | Praha |
GFA: | 771 m² |
GBA: | 4 377 m³ |
Zone: | 2 |
LoD: | 4 |
Output: | Model, 360° tour |
Input: | PDF, Point Cloud |
The model was created as a basis for the architectural study of the interior and subsequent phases. The project was focused on a part of the building. The model includes the main press hall, technical facilities and functionally associated rooms. The surveying was done by a stationary laser scanner in higher detail. The higher detail was further supplemented by a 360° tour of the rooms. Hidden structures were modelled based on archival documentation and information from the building managers.
Project name: | Modernization of the government meeting hall and vestibule |
---|---|
Year: | 2020 |
Location: | Praha |
GFA: | 302 m² |
GBA: | 2184 m³ |
Zone: | 2 |
LoD: | 4 |
Output: | Model, 360° tour |
Input: | Point Cloud |
The model was created as a basis for the architectural study of the interior and subsequent phases. The project focused on a part of the building. The model includes the main boardroom and its foyer. The measuring was done by a stationary laser scanner in higher detail. The higher detail was further supplemented by a 360° tour of the rooms. The hidden structures were modelled based on archival documentation and information from the building managers.
Project name: | National House Frýdek-Místek |
---|---|
Year: | 2020 |
Location: | Frýdek - Místek |
GFA: | 8 657 m² |
GBA: | 31 170 m³ |
Zone: | 4 |
LoD: | 4 |
Output: | Model, DWG, PDF, 360° tour |
Input: | PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The project includes two main building a service inner yard and service buildings. The measuring of all interior spaces was carried out with a stationary laser scanner in higher detail. The historic facades were also scanned in higher detail, for which 3D copies of the sculptural decoration were created within the model. A topographic plan was created for exterior areas. The higher detail was further supplemented by a 360° tour of the rooms. The hidden structures were plotted based on archival documentation and information from the building managers.
Project name: | University of Ostrava - LERCO II |
---|---|
Year: | 2020 |
Location: | Ostrava |
GFA: | 11 661 m² |
GBA: | 46 645 m³ |
Zone: | 2 |
LoD: | 2 |
Output: | Model |
Input: |
The model was created as a basis for the architectural study and subsequent phases. The modelled building was to be connected to the newly designed building. Great emphasis was put on the measurement of outdoor spaces and both vertical and horizontal communications. A topographic plan was created for the outdoor areas. The interior communications were surveyed with a stationary scanner. The wider context within the site was created in a separate model of lower detail. All work was carried out whilst the site was operational.
Project name: | Hotel Intercontinental, Prague |
---|---|
Year: | 2020 |
Location: | Praha |
GFA: | 3071 m² |
GBA: | 9562 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model |
Input: | DWG, point coordinates |
The model was created as a basis for the design phase. The building was measured with a stationary laser scanner. Surrounding areas and additional structural modifications of the building were point measured and linked to the model via a coordinate system. All documents were supplied by the client and no personal visit to the site was required.
Project name: | Pavilon AVU, passport |
---|---|
Year: | 2020 |
Location: | Brno |
GFA: | 525 m² |
GBA: | 2723 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | Point Cloud |
The model was created for facility management. The building was modelled based on data from a laser stationary scanner. Simplified drawings were generated from the model.
Project name: | AČR Tábor, Prokopa Holého |
---|---|
Year: | 2020 |
Location: | Tábor |
GFA: | 3457 m² |
GBA: | 12 964 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model, DWG, PDF, 360° tour |
Input: | PDF, Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model included the building and adjacent service areas. The building along with the outdoor areas was surveyed with a stationary laser scanner.
Project name: | MV_Kutná hora |
---|---|
Year: | 2020 |
Location: | Kutná Hora |
GFA: | 5316 m² |
GBA: | 18 118 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model |
Input: | PDF, Point Cloud |
The models were created as a basis for the design phase. The buildings were scanned with a mobile laser scanner. A topographical map was created for the entire site into which were linked other units. This created one model with sub-links, linked via coordinate system.
Project name: | BVV entrance |
---|---|
Year: | 2020 |
Location: | Brno |
GFA: | 212 m² |
GBA: | 977 m³ |
Zone: | 1 |
LoD: | 3 |
Output: | Model |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model comprised of the building and adjacent service areas. The building, along with the outdoor areas, was surveyed with a stationary laser scanner.
Project name: | MENDELU Object D |
---|---|
Year: | 2020 |
Location: | Brno |
GFA: | 2986 m² |
GBA: | 10 730 m³ |
Zone: | 2 |
LoD: | 3 |
Output: | Model |
Input: | Point Cloud |
The model was created as a basis for the architectural study and subsequent phases. The model included the building and adjacent service areas. The building, along with the outdoor areas, was surveyed with a stationary laser scanner.
Project name: | VUT, reconstruction of buildings |
---|---|
Year: | 2020 |
Location: | Brno |
GFA: | 39 551 m² |
GBA: | 155 299 m³ |
Zone: | 3 |
LoD: | 3 |
Output: | Model, 360° tour |
Input: | PDF, Point Cloud |
The models were created as a basis for the design phase. The buildings and the service areas of the buildings were measured with a stationary laser scanner. Topograpical plan was created for the outdoor hard surfaces and utilities. The entire surveying project was staged and a detailed schedule was developed for the project that included data acquisition, processing, and final conversion to the model.